New factory
coming soon

1

Million Sq.ft
Project

92

Million Sq.ft
of annual capacity

3

Kilns
- Two 200 meters/
One 82 meters

250

Thousand Sq.ft
automated warehouse

Intro image

U.S. Growth Strategy

Our US growth strategy was designed to combine Portobello Group’s integrated manufacturing and distribution expertise with a state-of-the-art production facility exclusively dedicated to the American market products and design trends.

In addition to a high scale and versatile production capability, incorporating the local culture with our American team will give us the competitive advantage to continue to grow and develop in the market, and create a solid national presence.

Portobello America will also generate new jobs and investment opportunities as a result of creating new ways of building a stronger relationship with Distributors nationwide.

“We are proud to soon present Portobello America’s new United States-based factory. We believe in the strategy, the market potential and, above all, the combination of our know-how with the American team and culture.”

Portobello Group’s CEO Cesar Gomes, Jr.

Location

Baxter TN is centrally located to where top-grade raw materials required for our production process can easily be sourced and procured.

It is logistically advantageous to about 80% of the U.S. population related to transit time and mileage to customers.
Also, the tile industry is growing exponentially with relation to supporting American manufacturers

#1

State in the United States for ball clay mining

#1

State for the growth in ceramics establishments

#1

State for growth in ceramics employment concentration

+2,300

Tennesseans employed in ceramics manufacturing

+40

Ceramics manufacturing establishments

$109

Million in ceramic products are exported annually from Tennessee.

Production Development

2023

Phase 1

Phase 1 will contain 2 Kilns, one 200 meters and one 82 meters, with an annual capacity of
52 million square feet.

2024

Phase 2

It is projected that a second kiln of 200 meters will be added to phase 2 in 2024, making a total of 3 kilns, increasing facility capacity to 92 million square feet.

2026

Phase 3

Future phases anticipate duplicating the capacity, adding three new kilns, and bringing the total facility to 6 kilns and an annual capacity of 184 million square feet.

52

million sq. ft

Production Development

2023

Phase 1

Phase 1 will contain 2 Kilns, one 200 meters and one 82 meters, with an annual capacity of
52 million square feet.

52

million sq. ft

2024

Phase 2

It is projected that a second kiln of 200 meters will be added to phase 2 in 2024, making a total of 3 kilns, increasing facility capacity to 92 million square feet.

92

million sq. ft

2026

Phase 3

Future phases anticipate duplicating the capacity, adding three new kilns, and bringing the total facility to 6 kilns and an annual capacity of 184 million square feet.

184

million sq. ft

Construction Gallery

October

2021

Factory Project Milestones

Milestones

Watch in real time